Telegraph Closures

TELEGRAPH ROAD OVERNIGHT CLOSURES
======================================
As part of the Woodrow Wilson Bridge Project, construction activities will require full ramp and lane closures of Telegraph Road and connecting ramps to the Capital Beltway in both directions for concrete girder placement under the Capital Beltway Inner Loop bridge. Rain delays have pushed back scheduled work by one day, with activities now expected to take place Thursday, Aug. 19, Monday, Aug. 23, and Tuesday, Aug. 24 between 10 p.m. and 5 a.m.

Crews will close one direction of Telegraph Road and corresponding ramps at a time, beginning with Telegraph Road North and the ramps to Eisenhower Avenue and the Outer Loop. Crews will begin taking lanes at 10 p.m. each evening with full closures by 11 p.m. All traffic will be restored by 5 a.m., prior to rush hour the following morning.

Thursday, Aug. 19 from 10 p.m. to 5 a.m. the following morning:
• Telegraph Road North will be closed to traffic.
• The ramp from Telegraph Road North to Eisenhower Avenue will be closed.
• The ramp from Telegraph Road North to the Outer Loop will be closed.

Monday, Aug. 23 from 10 p.m. to about 1 a.m.:
• Telegraph Road North will be closed to traffic.
• The ramp from Telegraph Road North to Eisenhower Avenue will be closed.
• The ramp from Telegraph Road North to the Outer Loop will be closed.

Monday, Aug. 23 (into Tuesday, Aug. 24) from about 1 a.m. to 5 a.m.:
• Telegraph Road South will be closed to traffic.
• The ramp from the Capital Beltway Inner Loop (I-95/495 South) to Telegraph Road South will be closed.

Tuesday, Aug. 24 from 10 p.m. to 5 a.m. the following morning:
• Telegraph Road South will be closed to traffic.
• The ramp from the Capital Beltway Inner Loop (I-95/495 South) to Telegraph Road South will be closed.